Tbilisi-Rustavi Highway Construction Works have Entered into an Active Phase

October 28, 2014

Tbilisi-Rustavi highway construction works are ongoing in full scale. Today First Deputy Minister of Regional Development and  Infrastructure  of Georgia, Municipal Development Fund of Georgia Executive Director - Giorgi Amashukeli, Tbilisi Mayor Davit Narmania, ADB President – Venchai Jangi visited civil works on Tbilisi Rustavi highway. The authorities entered into conversation with people employed at the project site and obtained detailed information on the progress of works

After project completion, distance from Tbilisi to Rustavi will take 15 minutes and conveyance will become the most safe and convenient, project is implemented by Municipal Development Fund.  

Civil works for the first and third sections of Tbilisi-Rustavi highway were launched on April 22 of current year.  Contract duration period is 17 months.  At the first stage, the first and third sections will be subjected to rehabilitation, cost of works amounts to GEL 88 761 128,95.  More than 250 workmen are employed on site including locals.

Estimated length of the design road is 17.4 kilometers. Considering complexity of the road alignment, the design road and respective design activities are divided into three following different sequences: First section – from the intercity bus terminal to the restaurant Marabda – 4km long.  Cross section of the road is a 6 lane one, with the 3.50m width for each lane. The central barrier is 6m wide. 2.5-3.0m width sidewalks for pedestrians will be arranged on both sides. Pavement is of asphalt concrete. The new road infrastructure includes one interchange, one traffic center and two bridges;

 Second section – densely populated Ponichala area – with estimated length of 6.8 kilometers. At this section, construction of  completely new, approximately 2km long urban type detour road is planned along the river Mtkvari.  Cross section of the road is a 4 lane one, with the 3.75m width for each lane. Pavement is of asphalt concrete. The new road infrastructure of this section includes: traffic centers, two underground passages, four  highway bridges and four pedestrian bridges; 

 Third section – from the “Socar” fuel station located at the Ponichala Settlement exit to the Rutsavi Motor Vehicle Fair - 6,6 kilometer long.  Cross section of the road is a 4 lane one, with the 3.75m width for each lane. The central barrier is 6m wide. Sidewalks are not envisaged.  Pavement is of cement-concrete. The new road infrastructure of this section includes: one interchange, one traffic center and two bridges.

As for the second section, its detailed design is completed and submitted to the ADB. Tender for this section will be announced separately.