New road with length of 5 km connecting 6 villages to Signagi and Tsnori .

June 5, 2015

Rehabilitation of Signagi municipality villages Bodbe and Bodboskhevi connecting road with length of 5 km  is implemented by MDF. Cost of the project amounts to GEL 2 831 384,37  and within the framework of Regional and Municipal Infrastructure development project II is financed by World Bank. More than 80 workmen are hired for civil works. MDF executive director Ilia Darchiashvili visited rehabilitation works.

First asphalt layer has already been arranged on 4 km section of mentioned road, and both layers on 2km section, on rest sections earth works are in progress.

 Rehabilitation will be completed in autumn of current year. Within the framework of the project following arrangements are in progress: paving, road bed, artificial structures, concrete culverts, metal pipes and shoulders cleaning. Also dismantling of damaged pipes and arrangement of a/c cover at yard entrances.

More than 6 villages are connected by this road to Signagi and Tsnori, mentioned road was entirely amortized. Since 1985 it has not been rehabilitated. As a result of road recovery journey up to Signagi and Stnori –( Kakheti’s important  trade and touring center )will become more easy. Also this is the shortest connecting road to capital city.