Documents
August 17, 2016
Georgian Sustainable Urban Transport Investment Program, Biannual Environmental Monitoring Report (EMR) for SUTIP 1
Sustainable Urban Transport Investment Program (ADB Loan 2655-GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement in Georgia. Biannual Environmental Monitoring Report for the projects implemented under the Tranche1 of the SUTIP, has been prepared by the Municipal Development Fund and covers the period of January-June, 2016.
August 17, 2016
Georgian Sustainable Urban Transport Investment Program, Environmental Monitoring Report for SUTIP 2
Environmental Monitoring Report for SUTIP 2
Sustainable Urban Transport Investment Program SUTIP 2 (ADB Loan 2879-GEO, 2880--GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement in Georgia.
This Environmental Monitoring Report was prepared as Environmental Audit Report to comply with the 2009 ADB’s SPS and Georgian legislation, including Safeguards Requirements and aims to identify past and present concerns from the construction activities of the “Modernization of Tbilisi-Rustavi Section of the Tbilisi-Red Bridge (Azerbaijani Border) Road (Sections 1 and 3)” Project that related to impacts on environment. The specific objectives of the audit are as follows:
Sustainable Urban Transport Investment Program SUTIP 2 (ADB Loan 2879-GEO, 2880--GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement in Georgia.
This Environmental Monitoring Report was prepared as Environmental Audit Report to comply with the 2009 ADB’s SPS and Georgian legislation, including Safeguards Requirements and aims to identify past and present concerns from the construction activities of the “Modernization of Tbilisi-Rustavi Section of the Tbilisi-Red Bridge (Azerbaijani Border) Road (Sections 1 and 3)” Project that related to impacts on environment. The specific objectives of the audit are as follows:
August 17, 2016
Georgian Sustainable Urban Transport Investment Program, Environmental Monitoring Report (EMR) for SUTIP 3
Sustainable Urban Transport Investment Program SUTIP 3 (ADB Loan 3063-GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement.
Environmental Monitoring Report (EMR) for the projects implemented under the SUTIP 3, has been prepared by the Municipal Development Fund and covers the period of April-June, 2016.
Environmental Monitoring Report (EMR) for the projects implemented under the SUTIP 3, has been prepared by the Municipal Development Fund and covers the period of April-June, 2016.
July 29, 2016
Municipality: Tbilisi
Donor: ADB
Georgian Sustainable Urban Transport Investment Program, Biannual Social Monitoring Report (SUTIP 3)
Sustainable Urban Transport Investment Program SUTIP 3 (ADB Loan 3063-GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement.
July 29, 2016
Arrangement of storm-water drainage system in Zemo Omalo, Akhmeta Municipality, Tusheti
The sub-project envisages arrangement of the storm water drainage system in the central square of the village Zemo Omalo. The SP will be implemented within the Regional Development Project (RDP) supported by World Bank.
July 29, 2016
Enhancing water supply system for village Omalo and arrangement of sewage system for hotel “Samzeo” in Omalo, Akhmeta Municipality, Tusheti
This Sub-project (SP) is a part of Public-Private Infrastructure (PPI) Investment Program and is delivered in support to Ltd “Samzeo”. The proposed SP envisages enhancing of the village water supply system, arrangement of the water supply and wastewater system for the hotel “Samzeo”.
July 8, 2016
Auditor’s Opinion
In 2016 independent audit companies “Deloitte“, „Grant Thornton”, "KPMG" conducted inspection of activities of the Fund for 2015 (from the standpoint of projects and Fund as an Orginization). As a result of auditory inspection, all directions of the activity has been evaluated positively. Please find Auditor’s Opinions as per the Fund (Organization) and projects as follows (please follow the link):
June 21, 2016
Preliminary Environmental Impact Assessments of the rehabilitation and operation of Tskaltubo and Telavi waste water treatment plants
Rehabilitation of the Tskaltubo and Telavi waste water treatment plants will be implemented within the Sustainable Wastewater Management Project (SWMP) financed by the Swedish International Development Cooperation Agency. The World Bank is the administrator of the SWMP.
June 8, 2016
Arrangement of a parking lot and upgrade of access road to Dariali Monastery residence (Kazbegi Municipality)
Under the sub-project it is planned arrangement of the parking territory and cement-concrete pavement on the access road to the monk’s cells via the church; arrangement of granite pavement adjacent area to Cells, arrangement of the wire mesh gabions.
May 25, 2016
Georgian Sustainable Urban Transport Investment Program, Biannual Environmental Monitoring Report (EMR) for SUTIP 3
Sustainable Urban Transport Investment Program SUTIP 3 (ADB Loan 3063-GEO) aims at development of the efficient, reliable and affordable urban infrastructure and service improvement.
Biannual Environmental Monitoring Report (EMR) for the projects implemented under the SUTIP 3, has been prepared by the Municipal Development Fund and covers the period of September, 2015 – February, 2016.
Biannual Environmental Monitoring Report (EMR) for the projects implemented under the SUTIP 3, has been prepared by the Municipal Development Fund and covers the period of September, 2015 – February, 2016.